GANTT Chart
Use this information to complete the GANTT chart, making sure to include all tasks, sub-tasks, interdependencies, and durations indicated (in weeks).
Task and Duration List:
- Requirements Analysis (2 weeks)
- Meetings and collecting requirements. Deliverable: Requirements document.
- Functional Specifications (3 weeks)
- Definition of the functionality, use cases, and acceptance criteria. Deliverable: Specifications document.
- Technical Specifications (3 weeks)
- High-level design and architecture. Deliverable: Architectural specifications.
- Detailed Specifications (4 weeks)
- Detailed design and modeling. Deliverable: Detailed specifications.
- Coding (8 weeks)
- Feature 1: Interface (3 weeks)
- Feature 2: Anomaly detector (5 weeks) – dependent on Feature 1
- Feature 3: Database (3 weeks) – dependent on Feature 1
- Feature 4: Rocket systems integration (5 weeks) – dependent on Features 1 and 2
- Unit testing (4 weeks)
- Testing of functions, valid detailed design.
- Integration testing (4 weeks)
- Testing of interactions, dependent on unit testing and a valid architectural design.
- System testing (4 weeks)
- Testing of the whole application, dependent on integration testing and valid requirements analysis.
- User acceptance (2 weeks)
- User testing, dependent on system testing.
- Deployment (1 week)
Once you’ve completed the chart, check that all tasks appear in the correct order and the dependencies are correctly indicated.